Home > Technical Informations

  Language
 
 


1. Dam Body

 

Back

1-1. Dam Body Specifications

·              Type  

: Earth- fill, with clay core.

·              Total volume of embankment

: 32.5(M.m3).

·              Crest level

: 234(m.) m.a.s.l.

·              Height from the Foundation

: 127(m.).

·              Crest length

: 3030(m.).

·              Crest width

: 12(m.).

·              Maximum width on the foundation

: 1100(m.).

·              Shell materials volume

: 19.6(M.m3).

·              Core materials volume

: 3.65(M.m3).

·              Excavation volume (Body & Spillway)

: 9.15(M.m3).

·              Slope of the upstream shell

: From the crest level, down to the level of 192 m.a.s.l., the slope is 1:2.25 (the shell on this location is covered with rip-rap). At this level a berm with 10(m.) width is executed, from thereof, the slope is 1:2.25, down to the level of 163 m.a.s.l. (this part of the shell until level 140(m.) is covered with soil- cement). At 163 m.a.s.l. level, another berm with 30(m.) length is executed. Then the shell reaches the foundation with the slope of 1:2.50 (which is the slope of the cofferdam upstream shell).

·              Slope of the downstream Shell

: At the cross section of the Kilometer 1+400, from the crest level of 234 m.a.s.l., down to the level of 200 m.a.s.l. , the slope is 1: 1.8. At this level a berm of 5(m.) width is executed. From thereof , the Shell keeps the same slope until the level of 170 m.a.s.l. At this level another berm of 84(m.) width is constructed. Then the Shell has been executed with the slope of 1: 1.8 , down to the level of 160 m.a.s.l. and 135 m.a.s.l., at which levels, two berms of 14(m.) and 75(m.) are constructed, consecutively. The Shell has been continued with the slope of 1:2 , until the toe of the Dam at the level of 116 m.a.s.l.

Back

1.2. Diversion System

Karkheh Dam diversion system, consists of: a concrete culvert with four waterways, intake structures, stilling basin, pre- cofferdam, cofferdam, and downstream dyke.

Back

1-2-1. Pre- cofferdam & cofferdam

In order to prevent the effect of water flow of the river, in the flood seasons, during construction of the Dam body, the upstream & downstream of the Dam were closed, by the means of cofferdam and downstream dyke. In this way the area between the two points became dewatered, then the construction activities of the main structure was rendered possible. Since the cofferdam of Karkheh Project is designed to be a part of the main dam, as a result, a pre- cofferdam was built, so that the Cofferdam could be constructed with the suitable technical specifications, in a dry condition.
The crest level of the pre- cofferdam, is designed to be at the level of 122.5 m.a.s.l., for a dry period, with the flood of 20- year- return- period, and the maximum discharge of 860(m3/s).
The design level of the cofferdam of Karkheh Diversion System is 163 m.a.s.l., for a flood of 100- year- return- period, with the discharge of 7240(m3/s), while a part of such flood (about 3680(m3/s)) will pass through the Diversion Galleries, and the rest, will be routed, in the Cofferdam Reservoir.

 

Back

1-2-2. Specifications of the Cofferdam

 

·         Length

: 950(m.)

·         Height from the river bed

: 52(m.)

·         Width of the crest

: 20(m.)

·         Maximum width on the foundation

: 495(m.)

·         Volume of the body

: 4.5(M.m3.)

·         Maximum storage volume

: 433(M.m3.)

Back

 

1-2-3. Downstream Dyke

According to the rating curve of the river, the water level on the downstream of the dyke is 115 m.a.s.l., with a discharge of 150(m3/s), and 120.5 m.a.s.l., for the flood with a discharge of 4570(m3/s). As a result, the crest of the downstream dyke is considered to be 121.5 m.a.s.l.

Back


1-2-4. Culvert
 

The diversion of the river from its original course, is a basic measure taken in the dam construction projects. Exploiting a four- concrete- waterway- culvert was considered to be the best choice for the Diversion System of Karkheh Project.
The specifications of this culvert is as bellow:
 

·             Shape

: four openings, with an octagonal section.

·             Dimension of each opening

: height: 10.5(m.),width: 5(m.).

·             Length (including the intake & outlet structures)

 

: 790(m.).

·             Type of lining

: reinforced concrete.

·             Excavation volume

: Apx. 1.5(M.m3).

·             Concreting volume

: 223,000(m3).

·             Inlet elevation

: 113 m.a.s.l.

·             Stilling basin bottom level

: 100 m.a.s.l.

·             Discharge capacity

: 3680(m3/s), at the level of 161.70 m.a.s.l. (before turning into a bottom outlet).

Back

 

1-2-5. Intake Structure

The intake Structure of the Diversion System, with the length of 32(m.) and the width of 30.6(m.), includes: four openings, intake tower, slots for the gates, and closure gates.
In order to close the water course through the waterways, gates of different types, have been installed, as bellow:
A) At waterways I &II, two bulk- head gates, the weight of each amounts to 32 tons.
B) At the waterway III, a fixed wheel gate, weighting 62 tons.
C) At the waterway IV, a roller gate, with the weight of 82 tons.
For the lifting & installation of the parts of the culvert gates, a cantilever gantry crane, with the capacity of 120 tons, was used. This crane which had been installed at the level of 160 m.a.s.l., on the crest of the intake tower was disassembled, after impounding and permanent closure of the gates.
On the upper part of the Intake tower, there are orifices and windows, which are used as inlets for the water flowing into the bottom outlet, after turning the culvert into the bottom outlet.

 

Back

1-2-6. Outlet Structure

In order to dissipate the energy of the water, passing through the culvert, a stilling basin- with the length of 128.5(m.), the width of 35(m.), and the bottom level of 100 m.a.s.l.- was constructed.
At the outlet of each waterway, some slots were designed, through which, the stop-logs were installed. By closing the gates, when necessary, flowing water into the waterways, is prevented.
 

Back

1-2-7. Bottom Outlet

Culvert waterways, are used as bottom outlet, during the operation of the Dam. To do this, in 50(m.) length of the waterways I,II & III, required pipes & valves are installed, so that the cross section of the water flow through the waterways, is decreased from 48(m2) to 3.14(m2), while their total discharge, in normal water level, has become limited. Waterway IV is completely closed, being used as an access road to the bottom outlet and the valves installed in other waterways. In the bottom outlet system, designed for the discharge control, two emergency and service gates are applied, each of which is opened and closed by a servo- motor, with the capacity of 175 tons.
 

Back

1-3. Watertightening System of the Foundation


In order to control seepage within the dam foundation, Grouting was considered as the first option. However, results of the trail grouting tests were not satisfactory. Therefore, other options for controling seepage in the foundation were studied, and eventually, a plastic concrete
cut-off-wall was selected for this purpose.
This main Cut- Off , which is on the same axis as the Dam body , is constructed under the foundation , in the center of the clay core.
Specifications
 

·          Length

: 2925(m.) .

·          Width

: 0.8-1 (m.).

·          Concrete volume

: 147370 (m3).

·          Minimum depth

: 18(m.).

·          Maximum depth

: 78(m.).

Since the Power- house Building is located on the left abutment, and having considered the effect of impounding , and seepage through conglomerate layers, as a result a Cut- Off- Wall was constructed too , under the east of the Power- house Building , for the protection and stabilizing the slopes on the Power- house area , and to minimize the seepage. To connect this Cut- Off to the main Cut- Off- Wall , a grout curtain has been executed through the access gallery , located on the Kilometer 0+950 . Thus , water seepage into the Power- house Building area is prevented.
Specifications Cut-Off-Wall, on the east of the
Power- house Building.
 

·          Length

: 750(m.).

·          Number of Panels

: 300.

·          Depth

: 20(m)- 70(m).

·          Apx. volume

: 30000(m3).


 

Back

1-4. Inspection & Access Galleries


Inspection Gallery
A concrete gallery was designed and constructed with the short distance from the Cut-Off- Wall, on the downstream, for the following purposes: a) access to the foundation, under the clay core, b) access to the Cut-Off- Wall, c) monitoring the Cut-Off- Wall, d) making possible repairs, during the Dam operation,
Other applications of this gallery could be as follows:
• Monitoring, and obtaining data concerning piezometric pressure of the water in different layers, under the Dam foundation.
• Possible increase of the depth, and improvement of the seepage flowing under the Dam foundation.
• Monitoring, and controlling the settlement of the Dam foundation.
• Possible drainage, and decreasing the water pressure of each geological layers under the Dam foundation.
• Inspection and identical observation of the conditions of the Dam foundation.
Specifications of the Inspection Gallery
 

·          Location

: under the clay core, 7.5(m.) downstream of the Cut-Off-Wall.

·          Length

: Apx. 1400(m.).

·          Height

: 3.2(m.) .

·          Width

: 2.6(m.).


Specification of Access Galleries
 

·          Number

: 3, constructed in the kilometers: 0+950. 1+450, and 2+160.

·          Total length of the 3 galleries

: Apx. 500(m.).

·          Total volume of concreting of the inspection & access galleries

 

: 50,000(m3).

Back

1-5. Instrumentations

In order to inspect the behavior of the foundation and the Dam body- during construction & operation- concerning pore pressure , earth pressure , seepage , and possible deviation of the body- about 1000 instruments have been installed in Karkheh Dam. These instruments are distributed in 23 sections of the body , according to the conditions of the foundation and the Dam height.
770 of which are of Cable Type , connected to the control room , on the left side of the body , the readings of which are done by the means of computer. While the readings of the rest are carried out on the installation locations , with the specific appliances of measurement. The data obtained from the instruments are inspected and analysed by the experts, periodically.

Back


1-6. Spillway

Having considered such parameters as the Dam height , the Reservoir volume , the type of the Dam , and its importance in: irrigation, hydroelectric power supply , the location of the Dam , regarding the downstream residential areas ,and the financial & social damages resulted from the Dam possible fracture , hence , the Spillway of Karkheh Dam has been designed based on the reliable discharge of probable maximum flood , considering suitable free – board.
 

Back


1-6-1. Specifications
 

·          Type

: gated.

·          Location

: right bank.

·          Discharge capacity

: 18260(m3/s)-(at PMF).

·          Total length

: 1118(m)(including the lengths of stilling basin & outlet channel).

·          Width

: 110(m) (excluding the middle piers, with the width of 90(m.)).

·          Stilling basin length

: 164(m).

·          Stilling basin width

: 110(m).

·          Design head on ogee crest

: 17(m).

·          Crest level of the ogee

: 209(m) m.a.s.l.

·          Excavation volume

: 5.5(M.m3).

·          Concrete volume

: 758000(M.m3).

Back

1-6-2. Spillway inlet Structure

The inlet structure of the spillway , which is a huge concrete structure , with the dimension of 110(m.) *59(m.) , includes : the ogee, the middle & the abutment piers , radial & stoplog gates , access bridge on the Dam crest , the bridge for the gantry crane , and hydromechanical equipment for the possible repairs of the gates. The ogee crest of the spillway is placed at the level of 209 m.a.s.l. , with the difference of 8(m.) height , comparing with the bottom of the approach channel at the level of 201 m.a.s.l.
Slope of upstream face of the ogee is 1 : 1 and the width of each of the middle piers of the spillway is 4(m.).
Six sets of radial gates are employed , to control the flow of water through the spillway , each with 18(m.) height , 15(m.) width , 22(m.) radius , and 170 tons of weight. This is one of the largest types , of radial gates, which, are manufactured in Iran. Each gate is operated by two servomotors, each of which, with the capacity of 26 tons and stroke of 11(m.) .
In order to repair the radial gates , four stoplogs are used , each with the 15(m.) of width , 3(m.) of height , and 30 tons of weight. For the purposes of shifting around or replacement of stoplogs , a gantry crane of 35 tons, with the rail length of 130(m.) , is exploited.

 

Back


1-6-3. Energy Dissipation System

A stilling basin has been constructed for reliable dissipation of energy, produced in the outlet flow. The stilling basin is of the U.S.B.R. 1 Type. Considering the secondary depth of hydraulic jump , and the level of the tail race, the level of the bottom of the stilling basin is designed to be at 95 m.a.s.l. The stilling basin length is 164(m.) , and its width is 110(m.). On the end part of the bottom of the stilling basin , the slope of 1:5 (V:H), from the level of 95 m.a.s.l. (along 65(m.) ) reaches up to the level of 108 m.a.s.l. The crest level of the side walls of the basin designed based on the maximum water level at the flood with 1000- year- return - period , including the free – board, amounting to 122.5 m.a.s.l.


 

Back


1-7. Borrow Pits
 

 

Borrow Pit

Borrow Pit area

(Km2)

Borrow Pit depth

(m)

Distance from the Site (Km)

Exploitable volume (M.m3)

Material type

 

Location

Coarse aggregate

G1

4

5-10

4-8

20

GW , GP

Shell, drain, filters, transition zones & concrete materials

G2

0.8

average 2

11-14

1.75

GW, GP, & a little GC

G3

8

average 3

9-12

2.5

GW, GP

Fine aggregate

C1

2.5

3-5

10-13

6.2

Weathered mudstone of CH

Clay core

Chenareh Mine

 

 

 

45

 

Limestone

rip-rap on the upstream face

GP : Poor graded sandy gravel.
GW : Well graded sandy gravel.
GC : Sandy gravel with clay.
CH : Non- organic clay, with high placticity.
* According to the test results, these materials are suitable for compaction, and their maximum dry density are more than 2.08(g/cm3).
** Insitu incompactibility test results indicate that the materials are suitable for the clay core.

Back


2. Hydroelectric power plant
2-1. General specifications

 

·           Power plant capacity

: 400(M.w.).

·           Number of the generators

: 3, each with the capacity of 133.3(M.w).

·           Annual average power production

: 934(G.wh.).

Back

 

2-2. Power plant Equipment
2-2-1. Cranes

Main cranes


Karkheh power plant has two over- head cranes , with each capacity of 225 tons. These cranes, by the means of a lifting beam- with the weight of about 20 tons- make possible the displacement & installation of the rotor of the generator (the heaviest equipment of the power- house , with the weight of 420 tons).
Each crane has an assisting winch , with the capacity of 40 tons , using for displacing and installing equipment , lighter than 40 tons.

Gantry Crane

This crane , with the capacity of 32 tons , is used for the installation of the stop- logs of the draft tube , at its outlet opening.

 

Back



2-2-2. Draft Tube Closure Gates
 

·           Type

: Stop- log.

·           Number of the gates

: 4 sets, totally 8 parts, which are able to close draft tubes of the two Units, simultaneously.

·           Weight of the lower part

:12924(kg.) (design weight).

·           Weight of the upper part

:13022(kg.) (design weight).

·           Total weight of the 4 sets of the gates

: 104 tons.

·           Operation mechanism

: hydraulic balance pressure, which is maintained by the means of bypass valves.

·           Gate pressure design head

: 24.48(m.).

·           Seal level of the bottom part of the gate

 

: 98.1 m.a.s.l.

·           Seals

: rubber J32 *85(m.m),on the side and upper parts, and flat- 12 * 70(m.m), on the lower part.

·           Location of the seals

: downstream.

·           Required time for the draft tube to be filled

 

: about 70 minutes.

The gates are placed (or displaced) by a lifting beam and the gantry crane , to or from the exact locations.

Back


2-2-3. Inlet Valves
 

·           Type

: Biplane Butterfly.

·           Number

: 3 sets.

·           Diameter

: 5.3(m.).

·           Design pressure

: 15 bars (1.5 (M.pa.)).

·           Hydrostatic test pressure

: 22.5 bars (2.25 (M.pa.)).

·           Maximum inlet discharge

: 159.54(m3.s).

·           Installation level of the valve center line

: 110.6 m.a.s.l.

·           Required time for the valve to be closed

: 60-90(s.).

·           Required time for the valve to be opened

: less than 120(s.).

·           Allowable leakage, at leakage test pressure of 1.154(M.pa.)

 

: maximum 13 liters per minute.

·           Number of servomotors of each valve

: 2 sets.

·           Diameter of each servomotor

: 700(mm.).

·                       Servomotor stroke

: 1655(mm.).

·           Operational oil pressure of each servomotor

 

: 60 bars (4 (M.pa.)).

·           Total weight of the complete set of  each butterfly valve of a Unit

 

: 223 tons (including its upstream & downstream pipes,bodies, bypass set, relief valve , and its control equipment, such as sump tank & oil pressure tank , electro- pumps, and servomotors).

Back

 

2-2-4. Weight of the Butterfly Valves Main Parts

·           Valve body

: 55.1 tons.

·           Disc

: 59 tons.

·           Upstream pipe

: 13.86 tons.

·           Downstream pipe

: 21.52 tons.

·           Total weight of the bypass pipes

: 3.32 tons.

The disc of the butterfly valve is closed under the force of the counter weights , connected to the valve shaft by the arms. It is opened by the servomotor force. In order to balance the hydraulic pressure of the two sides of the disc , when opening the hydraulic valves , two bypass pipes are exploited to allow water in the upstream pipes flow into downstream disc.

 

Back



2-2-5. Turbines
 

·           Type

: Francis , with the vertical axis (HLA-696 , LJ-450).

·           Number

: 3 sets.

·           Nominal rated head

: 93(m.).

·           Maximum head

: 106.5(m.).

·           Minimum head

: 62(m.).

·           Tail race level, when the 3 Units are operating

 

: 115 m.a.s.l.

·           Minimum tail race level (when one unit is operating with 50% of its nominal operation power

 

 

: 113.5 m.a.s.l.

·           Installation level of the turbine axis

: 110.6 m.a.s.l.

 

Turbine Output Power

·           At nominal height & the discharge of 158.42(m3/s)

 

: 136(M.w.).

·           At maximum height & the discharge of 159.54(m3/s)

 

: 156(M.w.).

·           At minimum height & the discharge of 127.95(m3/s)

 

: 70(M.w.).

·           Rotation velocity

: 150(R.P.M.).

·           Run away speed

: 288(R.P.M.).

·           Rotation direction

: clockwise.

·           Maximum thrust force of the shaft

: 6038(K.N.).

·           Hydraulic thrust at labirinth gap location

 

: 3748(K.N.).

·           Draft head

: -4.4(m.) (when the 3 units are operating at their maximum nominal power , with the height of 93(m)).

·           Runner diameter

: 4.5(m.).

·           Number of the runner blades

: 13.

·           Number of the wicket gates of the distributing set

 

: 24.

·           Design pressure of the spiral case

: 15 bars (1.5(M.pa.)).

·           Allowable leakage, from the wicket gates

 

: 560(lit/s) (at maximum heigth).

·           Turbine servomotors

: 2 sets , with the diameter of 420(mm.), and the stroke of 420(mm.).

·           Required time for the wicket gates to be closed

 

: 13(s.).

·           Turbine efficiency

: 94.1% (when operating at the nominal height & the discharge of 158.42(m3/s) , and output power of 136(M.w.).

·           Total weight of the turbine equipment of each Unit

 

: Apx. 700 tons.

·           Weight of the main equipment of the turbine of each Unit

 

: 560 tons (design weight).

·           Weight of the stay ring assembly

: 72 tons.

·           Weight of the spiral case assembly

: 146.7 tons.

·           Weight of the steel lining of the draft tube

 

: 54.86 tons.

·           Weight of the draft tube elbow

: 42.80 tons.

·           Weight of the draft tube cone

: 12.06 tons.

·           Weight of the steel lining of the turbine pit

 

: 14 tons.

·           Weight of the head cover assembly

: 45.5 tons.

·           Weight of the runner assembly

: 44.75 tons.

·           Weight of the shaft

: 26.9 tons.

Back

 

2-2-6. Governor System

·           Type

: Digital VGC211

·           Number

: 3.

·           Governor oil pump capacity

: 380(Lit/P.M.).

·           Number of the governor oil pumps

: 2.

·           Oil cooling pump capacity

: 40(Lit/P.M.).

·           Required time for the gate servomotor to be closed

 

: 11.5(s.).

·           Required time for the gate servomotor to be opened

 

: 13.5(s.).

·           Total capacity of the pressure oil tank

: 5500(lit.).

·           Normal pressure at pressure oil tank

: 40-60 bars.

·           Maximum operational pressure

: 64 bars.

·           Design pressure for the pressure oil tank

: 128 bars.

·           Pressure oil tank diameter

: 1.9(m.).

·           Pressure oil tank height (including safety valve)

 

: Apx. 3.2(m.).

Back

 

2-2-7. Generators

·           Type

: Synchronous vertical.

·           Number

: 3.

·           Maximum output

: 160(M.V.A.).

·           Nominal output

: 140(M.V.A.).

·           Number of phases

: 3.

·           Nominal power factor

: 0.95 .

·           Nominal voltage

: 13.8(K.V.).

·           Efficiency

: 98% (at nominal condition & 40( c)).

·           Frequency

: 5(Hz.).

·           Number of the poles

: 40 .

·           Velocity

: 150(R.P.m.).

·           Runaway speed

: 282(R.P.m.).

·           Fly wheel effect (GD2)

: 18000(ton/m2).

·           Rotor & stator winding insulation class

 

: class F .

·           Allowable temperature rise of the rotor & stator winding at nominal output condition

 

 

: less than 80(ºc) (ambient temperature , 40(ºc)).

·           Allowable temperature rise of the rotor & stator winding at maximum output condition

 

: less than 100(ºc) (ambient temperature , 40(ºc)).

·           Rotor weight

: Apx. 420(ton.).

·           Stator weight

: 164(ton.).

·           Weight of the shafts

: upper shaft: 4.7(ton.), lower shaft: 21.8(ton.).

·           Total weight of a generator

: 775(ton.).

·           Rotor diameter

: 8.462(mm.).

·           Stator diameter

: 10.5(mm.).

·           Number of the shoes of the thrust bearing

: 16 .

·           Maximum load of the thrust bearing , at full loading

 

: 1.119.900(K.g.).

·           Cooling system

: Air cooling , with the radiator.

·           Synchronous condenser capacity

: 100(MWAR).

Back

 

Generator Switchgear

·           Mechanism

: hydraulic (with charger spring).

·           Contact temperature rise

: 65(ºc).

·           Housing temperature rise

: 30(ºc).

·           Required time for the short circuit current to be cut

 

: 57(m.s.).

·           Maximum time for the contact to be closed

 

: 48(m.s.).

·           Minimum time for the contact to be opened

 

: 32(m.s.).

·           Maximum sparking time

: 60(m.s.).

Back

 

2-2-8. Excitation System

·          Type

: Static

·          Transformer type

:dried resinous.

·          Primary & secondary connections

: Yd5 .

·          Nominal capacity

: 1005(KVA).

·          Primary voltage

: .

·          Secondary voltage

: 350(v.) .

Back

 

2-2-9. Rectifier

·          Direct current (DC), at nominal capacity of the generator

 

: 1659(A) .

·          DC at maximum capacity of the generator

: 1781(A) .

·          Nominal DC voltage

: 182(V) .

Back

 

2-2-10. Field Installation
Main Contacts

 

·           Nominal current

: 2000(A) .

·           Maximum current

: 18000(A) .

·           Required time to be connected

: 0.06(s) .

·           Required time to be disconnected

: 0.30(s) .

·           Nominal voltage

: 550(V) .

 

Discharge Breaker

·          Nominal current

: 500(A) .

·          Maximum current

: 800(A) .

 

Brake Transformer

·           Capacity

: 300(KVA) .

·           Type of connections

: Yd5 .

·           Voltage

: 400/140(V.).

·           Short circuit current impedance

: 6%

Back

 

2-2-11. Busduct

·           Nominal voltage

: 13.8(K.V.) .

·           Maximum voltage

: 17.5(K.V.) .

·           Design voltage , with the network frequency

 

: 38(K.V.) .

·           Peak pulse voltage

: 95(K.V.) .

·           Main busduct nominal current

: 8000(A) for the conductor & 7600(A) for the duct.

·           Nominal branch current for the station service transformer

: 1200(A) for the conductor & 1140(A) for the duct.

·           Conductor temperature rise

: 65(ºc) (ambient temperature , 40(ºc)).

·           Duct temperature rise

: 40(ºc) (ambient temperature , 40(ºc)).

·           Main conductor diameter

: 300(m.m.).

·           Main duct diameter

: 825(m.m.).

·           Branch conductor diameter

: 148.7(m.m.).

·           Branch duct diameter

: 615(m.m.).

·           Main conductor section

: circle .

·           Branch conductor section

: square.

·           Moisture eliminator

: dry air .

·           Earthing System

: earthing through generator.

·           Main busduct length

: Apx. 30(m.) .

·           Branch busduct length

: Apx. 7(m.) .

·           Weight of each meter of the main busduct , for the 3 phases

 

: 245(Kg.) .

·           Weight of each meter of the branch busduct , for the 3 phases

 

: 144(Kg.) .

Back

 

2-2-12. Switches

Disconnector Switch

·           Mechanism

: electromotor.

·           Required time to be connected

: 2(s).

·           Required time to be disconnected

: 2(s).

·           Operating electromotor

: 38/6(A/V).

 

Earthing Switch

·           Type

: knife switch

·           Mechanism

: electromotor.

·           Required current to be connected & disconnected

 

: 4(A) , at 380(V).

·           Required time to be connected

: 2(s).

·           Required time to be disconnected

: 380(v) in 3 phases.

 

Short Circuit Current Breaker

 

·           Type

: electromotor.

·           Required time to be connected

: 2(s).

·           Required time to be disconnected

: 2(s).

·           Required current to be connected & disconnected

: 4(A).

 

Back

2-2-13. Arrester

 

·           Type

: polim/ICAR.

·           Discharge current

: 20(K.A).

·           Nominal voltage

: 21.25(K.A).

·           Maximum operating voltage

: 17(K.A).

 

Back

2-2-14. Transformers

Voltage Transformer

 

·          Type

: Dry

·          Temperature rise

: 65(ºc).

·          Primary nominal voltage

: 13.8(Kv.).

·          Maximum voltage

: 24(Kv.).

·          Peak pulse voltage

: 125(Kv.).

·          Peak pulse voltage with the network frequency

 

: 60(Kv.) per minute

·          Number of potential transformers (PT) on the generator side

 

: 2 , each with

.

·          Number of (PT)s on the main transformer side

 

: 1 , with .

·          (PT) class , on the generator side

: (15 VA, C1 0.5, 25 VA, C1 0.5) & ( 25 VA, C1 0.5, 15 VA, C1 3P)

·          (PT) class , on the main transformer side

: (3P/15 VA & 0.2/25KA)

 

Current Transformer

 

·           Type

: dry.

·           Number of (PT)s on the generator side

: 2 .

·           Number of (PT)s on the main transformer side

 

: 1.

·           (CT) class , on the generator side

: 2* (SP20/30 VA).

·           (CT) class , on the main transformer side

: 0.5 (M5/30 VA).

 

Back

2-2-15. Unit Protection System

 

·           Type

: numerical REG 216 .

·           Number of relay sets

: 2 relay sets for each unit.

·           Set A

: primary protections.

·           Set B

: secondary protections.

Back

 

2-2-16. Station Control System

 

·           Type

: distributed .

·           Unit control

: PLC

·           Controler type

:VME- BUS.

·           Network type

: Double star (Redundant).

·           Central control

: power plant control room, through two computer system & central control board.

Back

 

2-2-17. DC & UPS

·          Battery

: 2 sets , parallel .

·          Battery capacity

: 2000(Ah) .

·          Charger

: 2 sets .

·          UPS inverter

: 2 sets .

·          Capacity of each inverter

: 16(KVA) .

 

 

Back

 

2-2-18. DC & UPS low Voltage Equipment

·           Main distributing board of 220(VDC)

: 1, stable/ standing set.

·           Side distributing board of 220(VDC)

: 3, stable/ standing sets.

·           UPS distributing board

: 1 set , Wall Type.

·           Low voltage cables

: XLPE Type.

Back

 

2-2-19. Alternate current (AC)

 Station Service Transformer

·          Transformer type

:dried resinous.

·          Number

: 2 .

·          Capacity

: 1600(KVA) .

·          Voltage

: 13.8/0.4(KV.)

·          Vectorial group

: D Y n 1 .

·          Short circuit current in the primary winding

 

: 75(KA) .

·          Insulation class on the high voltage side

: class F .

·          Insulation class on low voltage side

: class H .

·          Allowable temperature rise

: 100(ºc) .

 

 

 

 Emergency Diesel Generator

·          Diesel type

: Perkins ,12 cylinder 3012/CV12 model.

·          Generator manufacturer

: Lury- Sumer .

·          Nominal capacity

: 600(K.V.A) .

·          Nominal velocity

: 1500(RPM.) .

·          Number of phases

: 3 .

·          Nominal voltage

: 400± 5% .

·          Power factor

: 0.85 pre- phase .

·          Weight

: Apx. 4600(Kg.) .

 

 Station Auxiliary Power

·          Number of transformer

: 1 , 33/4(K.V.) .

·          Vectorial group

: D Y n 1 .

·          Allowable temperature rise

: 75(ºc) .

·          Insulation class

: F.

 

 

 

Low Voltage Equipment

 

·          Main distributing board

: stable type , with the nominal voltage of 380(V.).

·          Low voltage cables

: all cables of XLPE Type.

 

 Low voltage Busducts

·          Type

: compact .

·          Nominal current

: 2500(A.) .

·          Nominal voltage

: 380(V.) .

·          Maximum voltage

: 1000(V.) .

·          Peak voltage at the network frequency

: 3(KV.) .

·          Short circuit current

: 80(KV.) .

·          Insulation class

: B .

·          Allowable temperature rise

: 50(ºc)(ambient temperature  40(ºc) ).

Back

 

2-2-20. Main Transformer

·          Number

: 3 .

·          Number of phases

: 3 .

·          Nominal power

: 160(M.V.A.)

·          Primary nominal voltage

: 13.8(K.V.)

·          Primary maximum voltage

: 17.5(K.V.)

·          Secondary nominal voltage

: 410± 2 * 2.5% (no- load condition).

·          Secondary maximum voltage

: 420(K.V.)

·          Short circuit current impedance

: Apx. 14% .

·          Vecorial group

: Ynd 11 .

·          Cooling system

: oil- directed & water- forced circulation (ODWF) .

·          Weight of each transformer with the side equipment & oil

 

: 154(ton.) .

·          Winding insulation class

: class A

·          Peak voltage with the network frequency in high voltage winding

 

: 630(K.V.)

·          Peak voltage with the network frequency in low voltage winding

 

: 38(K.V.)

·          Peak voltage with the network frequency in high voltage earth

 

: 50(K.V.)

·          Switching voltage

: 1050(K.V.)

·          Peak pulse voltage for high voltage

: 1425(K.V.)

·          Peak pulse voltage for low voltage

: 95(K.V.)

·          Peak pulse voltage for high voltage earth

: 125(K.V.)

·          Allowable oil temperature rise

: 50(ºc) .

·          Allowable winding temperature rise (in torrid zones)

 

: 68(ºc) .

·          Allowable winding temperature rise (in temperate zones)

 

: 55(ºc) .

·          Sliding distance of the high voltage bushings

 

: 11(m.) .

·          Total height of the transformer , including the bushing

 

: 9.4(m.) .

·          Transformer height up to the top of the oil tank

 

: 4.8(m.) .

Back

 

2-2-21. Switchyard

·          Type

: conventional- outdoor.

·          Nominal voltage

: 400(K.V.).

·          Breaker formation

: 1.5 defect breaker.

·          Number of the inlet feeder

: 3 .

·          Number of the outlet feeder

: 2 .

·          Peak voltage by the network frequency

: 520(K.V.) (rms).

·          Peak pulse voltage resulting from lightning

 

: 1425(K.V.) .

·          Peak pulse voltage, resulting from switching

 

: 1050(K.V.) .

·          Number & type of the breakers

: 5 sets, of SF6 Type.

·          Excavation volume

: 200,000(m3) .

·          Embankment volume

: 95,000(m3) .

·          Dimensions of the area

: 225 * 165(m) .

·          Type of the control building

: type I , with the dimension of 20.5 * 20.5(m) .

·          Concreting volume

: 3700(m3) .

Back

 

2-2-22. Transmission Lines

·          Type

: 2 bands , with (MCM- curlew 1033) cable).

·          Number

: 2 outlet lines.

·          Length

: Apx. 25(K.m) .

·          Connection

: Shushtar- Khorram- abad Line.

          Note: The largest part of Karkheh Power Plant Equipment is the butterfly valve, with the diameter of 5.3(m.) , and the heaviest part is the main transformer, with the weight of 120 tons (excluding the side equipment & the oil). As a result, for delivering , placement , and displacement of above mentioned parts , they are towed by a special machine.

Back

 

2-3. Power- house Building

 

·           Location.

: left bank water way of the Dam tail water, about 290(m.) from the Dam axis.

·           Type of the power- house.

: surface.

·           Length & width of the main hall containing the 3 Units & the erection bay.

 

:length: 97.5(m.), width: 26.5(m.).

·           Total length & width of the main hall , including other structures and the entrance room.

 

:length:117.5(m.), width: 55(m.).

·           Height , from the draft tube bottom , up to its upper part.

 

: 55(m.).

 

Back

2-4. Power- house tail race

          the power- house tail race consists of a six- opening- culvert, and an open channel , with the following specifications :

 

·           Length of the culvert

: 60(m.).

·           Length of the channel

: 300(m.).

·           Width of the culvert, at the power- house outlet

 

: 63.6(m.).

·           Height of the culvert from the bottom up to the top

 

: 23.4(m.),at the beginning, and 11.5(m.),at the end part.

·           Type of lining

: reinforced concrete.

·           Tail race water level

:115 m.a.s.l. (while operation of all the 3 Units).

·           Bottom level of the inlet opening of the culvert tail race

 

: 98.1 m.a.s.l.

·           Bottom level of the outlet opening of the culvert tail race

 

: 110 m.a.s.l.

Back

 

2-5. Power Tunnels

           Three individual tunnels have the duty of transferring water to the Karkheh Power- house. At the distance of 61(m.) from each tunnel inlet , there is a vertical shaft, with 80(m.) height , which is used for the installation, and complete closure of water flow , during possible repairs of the tunnel. To access to these shafts , a bridge of 60(m.) long , which is linked to the Dam crest , is used. The intake structure of the tunnels has six openings , each two openings of which , end to one of the tunnels. There is a trash - rack, with the width of 6.5(m.) and the height of 20(m.) , at each opening inlet.

 

 

 

 Specifications of the Power Tunnels

·           Tunnels lengths

:436(m.) ,446(m.),457(m.).

·           Tunnels diameters

:5.30-7.20(excavation diameter :8.6(m.)).

·           Type of lining

: reinforced concrete & steel lining.

·           Concrete lining length

: from the inlet opening until 15(m.) to the Cut- Off- Wall, with the length of about 125(m.) in each tunnel.

·           Steel lining length

: from 15(m.) , upstream of the Dam axis , up to the power- house location , with the total length of 970(m.)& total weight of 3722 tons.

·           Steel lining type

: ST 52.

·           Design pressure

: 1450(k.pa.).

·           Bottom level of the inlet opening

 

: 162 m.a.s.l.

·           Bottom level of the outlet opening

 

: 107.20 m.a.s.l.

·           Distances of the tunnels axes from one another

: 19(m.).

·           Total volume of concereting

: 120000(m3.).

·           Maximum outlet discharge of each tunnel

 

: 175(m3/s) .

·           Type of emergency gates

: roller.

·           Lifting system of the gates

: servomotor

·           Number of the gates

: 3 sets.

·           Dimensions of each gate

: 8.5(m.) *4.5(m.).

·           Weight of each gate

: 126 tons.

·           Type and capacity of the crane

: gantry, with the capacity of 25 tons.

·           Material of the trash rack plates

 

: ST 37.

·           Total weight of the trash racks

: 400 tons.

The lifting system of each gate , with the capacity of 300 tons and the stroke of 10.2(m.) , is located on the upper part of the inlet shafts , which is linked to the gate by 6 beams, each with the length of : 8.5(m.) .

Back

 

3. Dasht-e Abbas pressure Tunnel

          Required water for the irrigation of Dasht-e Abbas , Fakkeh , Eyn- Khosh , and Musian Plains , will directly be supplied by Karkheh Dam Reservoir , through Dasht- e Abbas Pressure Tunnel.

 

3-1. Specifications

·          Type of water flow

: pressure.

·          Inlet opening bottom level

: 176.5 m.a.s.l.

·          Outlet opening bottom level

: 175 m.a.s.l.

·          Slope of the tunnel

: 2.5/10000 .

·          Tunnel diameter

: 5.5(m.) (excavation diameter: 6.8(m.) ).

·          Tunnel length

: 6097(m.) .

·          Length of access tunnels

: 498(m.) .

·          Total volume of excavation

: 325,000(m3) .

·                      Total volume of concreting

: 82,000(m3) .

·          Concrete lining thickness

: 0.55(m.).

·          Steel lining length

: 50(m.) (end of the tunnel).

·          Steel lining material

: ST 52 .

·          Tunnel design discharge

: 80(m3/s) (maximum discharge: 120(m3/s) , at level of195 reservoir ).

Back

 

3-2. Tunnel Intake Structures

These structures include: trash- racks , slots for the stop- logs to be installed , and shafts & emergency gates. The trash- racks are of concrete, with the opening of 1.5* 1.5(m.) . The slots for the installation of the gates are positioned with a little distance from the trash- racks. There is a shaft , with 50(m.) height , in 285(m.) from the inlet opening, in which , there are emergency gates, for closing the tunnel, in emergency situations.
The emergency gates are of roller type , with the dimension of 3* 5 , and the total weight of 60(ton.) . These gates are operated by the means of a servomotor , with the capacity of 160(ton.) , and the stroke of 6.5(m.) . The servomotor is installed on the top of the shafts , at the level of 234 m.a.s.l. , connected to the emergency gates.
The frames of the emergency gates are of steel, executed 14(m.) from upstream of the gates , changing the circle section of the tunnel into a square shape , then at 14(m.) from downstream of the gates , the circle shape of the tunnel section is back again.
 

Back


3-3. Tunnel Outlet Structure

Dasht-e Abbas Tunnle is steel lined at the end, with the length of 50(m.) , at which location it is divided into two equal branches. The branches , also, contain steel lining of ST 52. There is a service gate (with a dimension of 1.8 * 2.6(m.)), and a radial gate (with a dimension of 1.7* 2.5(m.) )in each branch . The radial gate controls the outflow of water, and the service gate is used when repairs are needed. The radial gate is opened & closed by a servomotor of 20(ton.) , and another servomotor, with the capacity of 40(ton.) opens & closes the service gate.
A set of stop-log & a 12-ton over-head crane will be employed for the maintenance of the radial gates & the related equipment, installed in the tunnel branches.
 

Back


4. Access Roads and Bridges
• Road L1, with the length of 11.7(km.), is branched off from the main Road of Andimeshk- Dehloran, and is joined the Dam crest, through the left bank.
• Road L2, with the length of 21.8(km.), branches off from the main Road of Andimeshk- Ahwaz, and joins Road L1, on the left bank.
• The access road to the linking bridge, with the length of 3.4(km.), branches off from Road L1 and links to the existed road on the right bank, through the linking bridge.
• The constructed road, with the length of 19(km.), on the right bank of the Dam, which is branched off from Andimeshk- Dehloran Road, after passing through Naderi Bridge. This road links borrow pits of G1 and C1 to the Dam Site.
• A bridge, with the length of 205(m.), and the width of 13(m.) is constructed on the downstream of the Dam axis, in order to link access Roads L1 & L2 to the right bank of Karkheh River. Steel deck of which, with three 60- meter- bays and one 25- meter- bay, are installed on the reinforced concrete pile.
• Access road, with the length of 15(km.), to Dasht-e Abbas tunnel, branches off from Andimeshk- Dehloran.
 

Back

 

Table of Contents

General Informations
Technical Informations
Especial Informations
Essays Collection
Infos & News
Related Sites
Contact us
Karkheh Audio/Video
Weather Information